This page has updates from various sites in Umaria South.
U1 (Gilother):
Date: 30 june 2017
Update:
- 12000 holes completed
- fencing contract to be given; expected completion 30th july
- plantation completion 15th august
Latest pics:
U2 (Gilother pathari)
Date: 30 june 2017
Update:
- Boundary holes completed. Plantation expected august 10th. No other work this season.
- Old assets: 1000 guavas
Latest pics:
U3 (Majhwani)
Date: 30 june 2017
Update:
- Composite contract for 3000 holes plus boundary. Expected completion date 20 july.
- Plantation completion date august 10.
Latest pics:
U4 (Kohka)
Date: 30 june 2017
Update:
- Composite contract for 3000 holes plus boundary. Expected completion date 20 july.
- Plantation completion date august 10.
Latest pics:
U5 (Budia)
Date: 30 june 2017
Update: No work planned this monsoon
Latest pics:
U6 (Karonda)
Date: 30 june 2017
Update:
- full demakration done on june 25th
- no work planned yet
Latest pics:
U7 (Kadi Gadhari)
Date: 30 june 2017
Update: No work planned this monsoon
Latest pics: