Umaria South

This page has updates from various sites in Umaria South.

U1 (Gilother): 

Date: 30 june 2017

Update:

  • 12000 holes completed
  • fencing contract to be given; expected completion 30th july
  • plantation completion 15th august

Latest pics:

U2 (Gilother pathari)

Date: 30 june 2017

Update:

  • Boundary holes completed. Plantation expected august 10th. No other work this season.
  • Old assets: 1000 guavas

Latest pics:

U3 (Majhwani)

Date: 30 june 2017

Update:

  • Composite contract for 3000 holes plus boundary.  Expected completion date 20 july.
  • Plantation completion date august 10.

Latest pics:

 

U4 (Kohka)

Date: 30 june 2017

Update:

  • Composite contract for 3000 holes plus boundary.  Expected completion date 20 july.
  • Plantation completion date august 10.

Latest pics:

U5 (Budia)

Date: 30 june 2017

Update: No work planned this monsoon

Latest pics:

U6 (Karonda)

Date: 30 june 2017

Update:

  • full demakration done on june 25th
  • no work planned yet

Latest pics:

U7 (Kadi Gadhari)

Date: 30 june 2017

Update: No work planned this monsoon